Decision on the request by the TSO to derogate of the procedure for substantial modernisation (RfG network code Art 4.1 a) for electricity generation units with a maximum installed capacity < 25 MW and a voltage at the connection point >= 110 kV
1) Derogation request is complete with respect to the requirements defined in RfG Art.63 (2)
2) The provided CBA analysis, even if to a high degree qualitat...
see more
No negative consequences for market parties or system identified
1) Derogation of the procedure for substantial modernisation for electricity generation units with a maximum installed capacity < 25 MW and a voltage at the...
see more