Resolution on the request for derogation from compliance with the requirements established in the European Regulations approving the Grid Connection Network Codes for the Kurkudi Hydroelectric Power Plant (DCOOR/DE/006/25)
Consorcio de Aguas Bilbao Bizkaia
2025-07-14
If deemed Type A, a permanent extension of the LFSM-O response time and a temporary exemption from verification were requested.
If deemed Type B, a permane...
see more
Permanent partial exemption from Article 13.2 RfG (LFSM-O) under Type A classification, allowing response time extension from 8 to 40 seconds. Temporary exem...
see more
The plant’s very small size makes its impact on frequency regulation negligible, and the longer response time does not affect system stability. Hydraulic con...
see more
Permanent partial exemption applies for the lifetime of the generator, subject to review in the event of material technical or regulatory changes. 18-month t...
see more
NRA approved the request under a Type A classification (100 kW limitation), granting a permanent partial exemption for LFSM-O response time and a temporary e...
see more