Resolution granting a temporary derogation from compliance with the requirements established in the European Regulations approving the Grid Connection Network Codes for the wind farms integrated in the MONEGROS Cluster (DCOOR/DE/011/23)
Owners of the 12 wind farms forming the MONEGROS Cluster
2023-12-22
Articles of Regulation (EU) 2016/631 (RfG):
o Article 13.2 (Limited Frequency Sensitive Mode – Overfrequency, LFSM-O)
o Articles 15.2(a) and 15.2(b) (Activ...
see more
Temporary derogation granted until 2 October 2024 for Articles 13.2, 15.2(a), 15.2(b), 15.2(c), 15.2(d), 18.2(b), 18.2(c), and 21.3(d) of Regulation (EU) 201...
see more
• The non-compliance results from an incorrect interpretation during the design phase (shared PPC controller), not from technical incapacity.
• There is a f...
see more
• Obligation to implement the necessary technical modifications.
• Obligation to obtain the Final Operational Notification (FON) before 2 October 2024.
• I...
see more
A temporary derogation is granted to the MONEGROS Cluster to allow implementation of technical corrective measures ensuring full compliance with the RfG, wit...
see more