Derogation Decision details


General information

Resolution granting a temporary derogation from compliance with the requirements established in the European Regulations approving the Grid Connection Network Codes for the wind farms integrated in the MONEGROS Cluster (DCOOR/DE/011/23)
Owners of the 12 wind farms forming the MONEGROS Cluster
2023-12-22
Articles of Regulation (EU) 2016/631 (RfG): o Article 13.2 (Limited Frequency Sensitive Mode – Overfrequency, LFSM-O) o Articles 15.2(a) and 15.2(b) (Activ... see more
Yes
Network code specific

RfG
C, D
12
487.000
Decision related

2024-02-15
Yes
Temporary derogation granted until 2 October 2024 for Articles 13.2, 15.2(a), 15.2(b), 15.2(c), 15.2(d), 18.2(b), 18.2(c), and 21.3(d) of Regulation (EU) 201... see more
• The non-compliance results from an incorrect interpretation during the design phase (shared PPC controller), not from technical incapacity. • There is a f... see more
• Obligation to implement the necessary technical modifications. • Obligation to obtain the Final Operational Notification (FON) before 2 October 2024. • I... see more
A temporary derogation is granted to the MONEGROS Cluster to allow implementation of technical corrective measures ensuring full compliance with the RfG, wit... see more