Data item details


Name
Levelised cost of hydrogen produced by electrolysers connected directly to onshore wind in the EU Member States – October 2025 (EUR/kg and EUR/MWh)
Source
ACER, based on the European Hydrogen Observatory LCOH calculator.
Identifier
Reference
Figure 33
Comment
The default technoeconomic assumptions of the LCOH calculator were used. Electricity consumption-related taxes were not considered. For onshore wind the tool assumes direct connection between the electrolyser and the wind farm.

Data item data can be filtered and exported as an Excel file.
The reason for exporting is asked during export once per session.


2025-11-28 18:21


Fields to export

Country Cost component Value [EUR/kg] Value [EUR/MWh]
IrelandTotal levelised cost of hydrogen4.60139.30
IrelandCapital expenditure2.1064.30
IrelandElectricity1.8053.80
IrelandOther operating expenditure0.7021.30
NetherlandsTotal levelised cost of hydrogen5.60167.60
NetherlandsCapital expenditure2.5075.10
NetherlandsElectricity2.3067.60
NetherlandsOther operating expenditure0.8024.90
DenmarkTotal levelised cost of hydrogen5.80175.40
DenmarkCapital expenditure2.6078.40
DenmarkElectricity2.4071.20
DenmarkOther operating expenditure0.9025.80
FinlandTotal levelised cost of hydrogen6.40192.50
FinlandCapital expenditure3.0089.50
FinlandElectricity2.4073.30
FinlandOther operating expenditure1.0029.70
SpainTotal levelised cost of hydrogen6.50195.20
SpainCapital expenditure3.0091.00
SpainElectricity2.5073.90
SpainOther operating expenditure1.0030.30
LithuaniaTotal levelised cost of hydrogen6.80203.90
LithuaniaCapital expenditure3.0090.40
LithuaniaElectricity2.8083.50
LithuaniaOther operating expenditure1.0030.00
MaltaTotal levelised cost of hydrogen6.80204.50
MaltaCapital expenditure3.1093.70
MaltaElectricity2.9086.80
MaltaOther operating expenditure0.8024.00
SwedenTotal levelised cost of hydrogen6.80205.10
SwedenCapital expenditure3.0090.70
SwedenElectricity2.8084.40
SwedenOther operating expenditure1.0030.00
PolandTotal levelised cost of hydrogen6.90206.90
PolandCapital expenditure3.0088.60
PolandElectricity3.0088.90
PolandOther operating expenditure1.0029.40
GermanyTotal levelised cost of hydrogen6.90208.10
GermanyCapital expenditure3.0088.60
GermanyElectricity3.0090.10
GermanyOther operating expenditure1.0029.40
CroatiaTotal levelised cost of hydrogen6.90208.10
CroatiaCapital expenditure3.1092.20
CroatiaElectricity2.8085.30
CroatiaOther operating expenditure1.0030.60
EstoniaTotal levelised cost of hydrogen7.00209.60
EstoniaCapital expenditure3.1092.80
EstoniaElectricity2.9085.90
EstoniaOther operating expenditure1.0030.90
ItalyTotal levelised cost of hydrogen7.00211.40
ItalyCapital expenditure3.40102.10
ItalyElectricity2.8083.20
ItalyOther operating expenditure0.9026.10
LatviaTotal levelised cost of hydrogen7.60228.50
LatviaCapital expenditure3.50104.80
LatviaElectricity3.2097.00
LatviaOther operating expenditure0.9026.70
FranceTotal levelised cost of hydrogen7.70230.30
FranceCapital expenditure3.40101.50
FranceElectricity3.40103.00
FranceOther operating expenditure0.9025.80
GreeceTotal levelised cost of hydrogen7.90235.70
GreeceCapital expenditure3.40101.80
GreeceElectricity3.60108.10
GreeceOther operating expenditure0.9025.80
AustriaTotal levelised cost of hydrogen7.90238.40
AustriaCapital expenditure3.60109.30
AustriaElectricity3.40101.20
AustriaOther operating expenditure0.9027.90
CzechiaTotal levelised cost of hydrogen8.00238.70
CzechiaCapital expenditure3.70109.60
CzechiaElectricity3.40101.20
CzechiaOther operating expenditure0.9027.90
SlovakiaTotal levelised cost of hydrogen8.80263.40
SlovakiaCapital expenditure4.00120.70
SlovakiaElectricity3.70111.70
SlovakiaOther operating expenditure1.0030.90
PortugalTotal levelised cost of hydrogen8.80265.50
PortugalCapital expenditure4.10121.90
PortugalElectricity3.80112.60
PortugalOther operating expenditure1.0030.90
SloveniaTotal levelised cost of hydrogen9.00270.30
SloveniaCapital expenditure4.10124.00
SloveniaElectricity3.80114.70
SloveniaOther operating expenditure1.1031.50
BelgiumTotal levelised cost of hydrogen9.30278.40
BelgiumCapital expenditure4.30127.60
BelgiumElectricity3.90118.30
BelgiumOther operating expenditure1.1032.40
HungaryTotal levelised cost of hydrogen9.40281.70
HungaryCapital expenditure4.30129.10
HungaryElectricity4.00119.50
HungaryOther operating expenditure1.1033.00
BulgariaTotal levelised cost of hydrogen9.50284.40
BulgariaCapital expenditure4.30130.30
BulgariaElectricity4.00120.70
BulgariaOther operating expenditure1.1033.30
RomaniaTotal levelised cost of hydrogen9.50285.00
RomaniaCapital expenditure4.40130.60
RomaniaElectricity4.00121.00
RomaniaOther operating expenditure1.1033.30
LuxembourgTotal levelised cost of hydrogen9.70292.20
LuxembourgCapital expenditure4.50133.90
LuxembourgElectricity4.10124.00
LuxembourgOther operating expenditure1.1034.20
CyprusTotal levelised cost of hydrogen9.80293.40
CyprusCapital expenditure4.50134.50
CyprusElectricity4.20124.60
CyprusOther operating expenditure1.1034.20