Name
Electrolysers under construction with expected commissioning by 2026 by end-use – September 2024 (MW)
Source
ACER based on data from the European Hydrogen Observatory.
Identifier
Reference
Figure 29
Comment
Data reflects the known electrolysers under construction as of May 2024.
Data item data can be filtered and exported as an Excel file.
The reason for exporting is asked during export once per session.
Fig29
Download as CSV
Download as Excel
Download filtered data
Download whole data
Clear filters
End-use (groups)
Ammonia
Blending
E-fuels
Industrial heat
Methanol
Mobility
Other industry
Power generation
Refining
Residential heat
Steel
Total
Production capacity (MW)
10
120
1781
22
3
30
4
47
5
574
59
870
Fields to export
End-use (groups)
Production capacity (MW)
Steel
870
Refining
574
Methanol
120
Mobility
59
Other industry
47
E-fuels
30
Power generation
22
Ammonia
10
Blending
5
Residential heat
4
Industrial heat
3
Total
1781
What is the purpose of your download?
×
Please specify your reason for exporting data.
Download reason
Research
Commercial
Curiosity
Data analysis
Study
Other
Please specify
OK
Cancel